Construction Project Updates

We ask all students, faculty, staff and visitors to stay alert during the construction of the new Biological Sciences building. You will need to plan for extra time to get to various locations in the heart of campus during construction. The construction zone will encompass the area from Oceanography and Physical Sciences at the pond bridge and extend east to the Elizabeth River Trail. The construction of the new building site is at the center of Oceanography and Physical Sciences building, Mills-Goodwin building and the Webb Center.ÌýAdditionally, construction activities will occupy the oval between Perry Library and Engineering Systems Building.

Your safety is our top priority, and we ask that you visit this site often for construction updates and prepare for extra time to get to your various destinations around campus.Ìý

Project Stages

Biology Construction Map

Fencing was erected around the perimeter of the entire project and construction laydown area beginning the week of May 12, 2025 and was completed by May 23, 2025.

There will be two scheduled power outages to isolate the existing transformers onsite. The first scheduled is onÌýMay 13Ìýand the second one is scheduled forÌýMay 16 between 5:00 a.m. to 7:00 a.m., to impact the following buildings:

  • Engineering and Computational Science Building (ECSB)
  • Engineering Systems Building (ESB)

  • Kauffman Hall

  • Monarch Hall

  • Center for Implementation and Evaluation of Education Systems (CIEES)

  • Children's Learning and Research Center (CLRC Building 2) - Preschool (Lions Club Child Study Center)

Demolition Updates:

Demolition of the following three buildings, Alfriend Chemistry, Pretlow Planetarium, and the Arthur and Phyllis Kaplan Orchid Conservatory began on Tuesday, May 27, 2025, and was completed by July 31, 2025.ÌýConstruction to followÌýimmediately after demolition.Ìý

Ìý

Demolition was completed as of July 31, 2025. Construction will commence with pile driving operations followed by concrete structural frame erection.Ìý

Ìý

Ìý

Ìý

Work Scheduled Dates of Scheduled Work
Pile Driving Test piles will begin week of August 8, 2025 and pile driving work to last until mid-November 2025.Ìý

Ìý

Biology Construction Map

Fencing was erected around the perimeter of the entire project and construction laydown area beginning the week of May 12, 2025 and was completed by May 23, 2025.

There will be two scheduled power outages to isolate the existing transformers onsite. The first scheduled is onÌýMay 13Ìýand the second one is scheduled forÌýMay 16 between 5:00 a.m. to 7:00 a.m., to impact the following buildings:

  • Engineering and Computational Science Building (ECSB)
  • Engineering Systems Building (ESB)

  • Kauffman Hall

  • Monarch Hall

  • Center for Implementation and Evaluation of Education Systems (CIEES)

  • Children's Learning and Research Center (CLRC Building 2) - Preschool (Lions Club Child Study Center)

Demolition Updates:

Demolition of the following three buildings, Alfriend Chemistry, Pretlow Planetarium, and the Arthur and Phyllis Kaplan Orchid Conservatory began on Tuesday, May 27, 2025, and was completed by July 31, 2025.ÌýConstruction to followÌýimmediately after demolition.Ìý

Ìý

Demolition was completed as of July 31, 2025. Construction will commence with pile driving operations followed by concrete structural frame erection.Ìý

Ìý

Ìý

Ìý

Work Scheduled Dates of Scheduled Work
Pile Driving Test piles will begin week of August 8, 2025 and pile driving work to last until mid-November 2025.Ìý

Ìý